Massachusetts Maritime Academy
Client: Massachusetts Maritime Academy
Project Location: Buzzards Bay, Massachusetts
Project Size: 10,000 SF
Project Type: Roof Replacement
Scope:
Massachusetts Maritime Academy required a roof system replacement at the Facilities Department Building due to several ongoing active leaks both under the original roof which was installed in 1999 and a section of rubber roof which was replaced in 2020.
Services:
- Removal of existing roof system down to the structural deck. 
- Remove and dispose of the existing 80 square PVC roof assembly and all components, down to the wooden deck. 
- Install new drains to meet state plumbing codes. 
- Mechanically attach flat & tapered polyisocyanurate insulation, per wind-uplift test adhesion patterns and to meet building code. 
- Adhere ½” gypsum coverboard in foam insulation adhesive. 
- Adhere 2 modified base plies to gypsum coverboard in cold adhesive at rate of 2.5 gallons per sq. 
- Adhere mineral surface modified cap sheet to base ply in cold adhesive at rate of 2.5 gallons per sq. 
- Attach ANSI-SPRI certified metal edge system. 
 
        
        
      
           
        
        
      
           
        
        
      
           
        
        
      
    